Specification checklist for exposed-aggregate pool finishes: an architect’s guide

Last updated:

A practical specification checklist for architects and pool builders covering sample approval, area calculation, substrate acceptance, edge detailing, and start-up care for exposed-aggregate pool finishes.

Specifying a cement-based exposed-aggregate pool finish requires defining the finish, interfaces, responsibilities, and acceptance requirements rather than simply naming a colour on a drawing. Because the finish is a decorative layer—not structural repair or waterproofing—the specification must coordinate sample approval, area measurement, substrate acceptance, transition detailing, and initial water care to align the design team, main contractor, and specialist applicator.

1. material line, colour, and sample approval

Start by matching the surface texture and underwater response to the architectural setting. Within the PebbleCrete range manufactured in Phuket, Thailand, all three lines are cement-based finishes applied at a nominal 10 mm thickness.

Include three sample verification items in the specification:

2. measured finish area and application scope

Separating material supply, preparatory works, and specialist installation prevents scope gaps between trade packages.

3. substrate, render, and waterproofing acceptance

In the pool system build-up, wall alignment, floor falls, step geometry, and level corrections belong to the prepared watertight base and render—not to the finishing coat.

4. movement joints, transitions, and fittings

Resolve junction details and hardware clearances on drawings before the applicator arrives on site.

5. water treatment and start-up responsibilities

Across Southeast Asia and the Middle East, high ambient temperatures and variable source water make handover planning essential. Well, river, or lake water can arrive at pH 5.5; adding trichlor without correcting pH and alkalinity can visibly etch a cement-based finish within six months.

6. documents to request and service life planning

State your company name, the project name and country, and the product line to request current project documentation from PebbleCrete before work begins:

As a planning figure, an exposed-aggregate pool finish is generally expected to serve for 15–20 years. This is an industry estimate, not a warranty term. Where an individual pool falls within or outside that range depends on substrate preparation, application quality, water chemistry and routine maintenance.

Frequently asked questions

What should a specification for an exposed-aggregate pool finish cover?

Six items: the material line, exact colour and approved wet sample and mock-up; the measured finish area and who supplies and applies what; substrate, render and waterproofing acceptance; movement joints, waterline, step markers and fittings; filling-water, start-up and operating targets with a named operator; and the current PebbleCrete project documents and material warranty. The finish is decorative and does not replace waterproofing or structural repair.

Does an exposed-aggregate finish waterproof the pool shell?

No. A cement-based exposed-aggregate finish is a decorative layer and does not replace structural repairs or waterproofing. The concrete shell, render, waterproofing system, and water test must be specified and formally accepted before the finish is applied.

Why must architects specify both a wet physical sample review and an on-site mock-up?

Screen images cannot reproduce how natural stone, glass aggregate, and hand application interact with water depth and daylight. Viewing a physical sample under water confirms the colour choice, while an on-site mock-up sets an agreed benchmark for surface appearance and texture alongside separately documented workmanship and acceptance criteria.

Why should the specification cover filling water and the first month of operation?

A newly completed finish is vulnerable to acidic water, metal staining, and site debris during its early weeks. Specifying pre-tested fill water, an agreed start-up plan under current approved start-up instructions, daily brushing, and a pH target of 7.6–7.8 helps prevent avoidable early surface damage and reduces risk before operator handover, alongside project-specific care.

Photographs and screen colours are illustrations. Confirm colour and texture with a current physical sample viewed wet and an approved on-site mock-up.

This article provides general technical guidance, not a design, installation or safety instruction for a specific pool. Every project depends on its structure, substrate, waterproofing, water conditions and local regulations. Refer to the current PebbleCrete technical documents: the Technical Data Sheet and the Installation Overview are available online, and the Safety Data Sheet and the full Method Statement are issued on request. Confirm structural, waterproofing, electrical and installation decisions with qualified professionals. PebbleCrete supplies the material only; unless agreed otherwise in writing, substrate preparation and application are carried out by the owner’s applicator, who is responsible for that work. Nothing in this article limits your statutory rights.