A specification and handover guide for detailing the junction between a cement-based exposed-aggregate pool finish and underwater acrylic or glass panels.
In short: Where a cement-based exposed-aggregate finish such as PebbleCrete meets an acrylic or glass pool window, detail the junction on construction drawings before site work starts. The specification should assign trade responsibilities, define a substrate rebate and include a flexible sealant recess confirmed by the window supplier and project designer. Because the finish is decorative, the project’s engineered window support, sealing and shell waterproofing arrangements must be completed, water-tested at the stage agreed by the pool designer before work is covered, and accepted before finishing.
Separating Waterproofing, Glazing Seals and the Decorative Finish
Whether a pool in Southeast Asia, the Middle East or another warm climate uses PebbleCrete Classic, PebbleCrete Supreme or PebbleCrete Glass, an exposed-aggregate finish is strictly a decorative layer, not a structural repair or waterproofing barrier.
Watertightness depends on the shell and the project’s engineered window support, sealing and waterproofing arrangements, designed by the named responsible specialists. The cementitious finish is decorative and does not stop leaks, while the perimeter sealant’s watertightness role must be defined by the window supplier and project designer. Shell waterproofing and window assemblies must be water-tested at the stage agreed by the pool designer before relevant work is covered, with written acceptance recorded before finishing.
Deciding Who Details and Coordinates the Junction
Improvising the window junction on site creates gaps between trades. Assign responsibilities during design development and show the coordinated detail on construction drawings:
- The window or acrylic supplier defines rebate dimensions, movement tolerances, panel expansion, protection requirements, and perimeter sealant geometry, compatibility criteria and watertightness role.
- The pool designer or architect coordinates the shell, render, waterproofing continuity and alignment so the finish meets the panel cleanly at floors, walls, steps, waterlines and overflow lips.
- The finish applicator reviews the drawn termination edge for buildability, checks that the substrate matches the agreed detail, and produces an on-site mock-up. PebbleCrete supplies the finishing material; unless agreed otherwise in writing, application, mock-ups and finished results remain the owner’s and applicator’s responsibility.
Naming these roles in the specification clarifies who forms, inspects and accepts the opening and prepared base before finishing.
Showing a Defined Edge and Flexible Sealant Joint on Drawings
A concrete shell with a cement-based finish and an acrylic or glass panel behave differently under water load, thermal shifts and settlement. Specify the termination profile in the approved junction detail so the substrate rebate accommodates the specified finish build-up rather than tapering the edge or butting rigidly against the panel:
- A defined termination edge or rebate: The prepared substrate must present a solid, true margin; alignment, recess geometry and level corrections belong to substrate preparation.
- Allowance for a flexible sealant joint: Include a movement recess separating the finish from the panel. Confirmed by the project designer and window supplier, this joint accommodates specified differential movement, limiting stress transfer to the panel and reducing the risk of the finish edge spalling.
- Joint selection with the window supplier: Obtain documented compatibility confirmation for the panel, sealant, backing materials and exposure conditions to reduce the risk of crazing or staining the glazing.
- Continuity at edges and waterlines: Where a panel meets a coping, overflow edge or waterline, detail how the joint continues across the air–water interface and confirm finish and sealant suitability for waterlines, overflow edges and repeatedly wetted and dried areas.
Specifying Visual Alignment, Physical Samples and Mock-Ups
Because water depth and lighting change how a finish reads against clear glazing, rely on physical references rather than screen images. When specifying PebbleCrete Classic, PebbleCrete Supreme or PebbleCrete Glass beside a window, record the material family, exact colour and sample reference together, review a current wet sample with the proposed sealant colour, and require an on-site mock-up of the approved termination and sealant detail.
Protecting Acrylic and Glass Panels During Pool Works
Site preparation and finishing work adjacent to glazing carry a risk of scratching, dust and chemical marking. Specify protection against scratching, impact and chemical contamination agreed with the window supplier:
- Supplier-approved coverings: Install protective sheeting or boarding approved by the window supplier, following their coverage, attachment, access and removal instructions.
- Completion of adjacent heavy works: Complete and clean away overhead work, grinding, tiling and repairs before finishing.
- Containment and contamination control: Enforce supplier-approved protection, masking and run-off control during adjacent works so preparation or finishing materials do not contact the panel or seals – including the cement-laden water from exposing the aggregate and the applicator’s specified final wash, which must not run over or dry on the panel.
- Documented condition checks: Photograph the panel and protection before and after finishing, recording in the contract who removes protection before filling.
Inspection and Acceptance at Handover
Review the junction at substrate acceptance, upon completion of the finish and sealant, and during pool start-up. The sealant joint between the finish and the panel can only be formed after the finish is complete, while the finish must be filled promptly once the installer releases the pool. Agree in advance with the window supplier and the applicator which sealant is used, how long it must cure before immersion and where it sits in the start-up programme. Confirm whether the window’s primary watertight seal depends on this joint; where it does, its cure time governs the filling date, and that must be written into the programme before finishing starts. At handover, inspect against the drawings, wet sample and mock-up:
- Clean visual edge: The finish meets the recess in a straight line without ragged edges, steps in level or cement bridging.
- Sound sealant profile: Visually verify that the sealant joint is continuous, smooth and evenly finished to the approved profile with no visible voids or detachment, supported by any documented adhesion or verification checks required by the specification.
- Surface consistency: Assess the finish against the approved wet sample and mock-up, allowing agreed variation in colour, texture and particle distribution while investigating pronounced irregularities.
- Unmarked glazing and records: Once the designated contractor removes protection, confirm an unmarked panel and a handover file with substrate sign-off, water-test records, sample reference and supplier confirmation.
Ongoing Care and Inspection of the Sealant Joint
A cement-based decorative finish depends on substrate preparation, application quality, water chemistry and routine maintenance, whereas the perimeter sealant joint is a serviceable component that ages differently. Handover documentation should establish:
- Periodic joint inspections: Visually inspect the perimeter sealant on a scheduled basis for softening, hardening, shrinkage, detachment, tearing or biological growth.
- Balanced water chemistry and safe dosing: Maintain water within the PebbleCrete targets (pH 7.6–7.8, free chlorine 1–3 ppm, total alkalinity 80–120 ppm, calcium hardness 200–400 ppm), log tests and additions, and follow approved dosing instructions. Never add any form of chlorine directly onto the finish or broadcast it across the pool; always dose chlorine into the balance tank, or failing that the skimmer.
- Non-abrasive cleaning: Clean the window and joint using only soft equipment and products approved by the window supplier, avoiding abrasive pads or acid cleaning.
- Planned joint renewal: When inspection shows sealant wear or degradation, arrange a specialist assessment and follow a renewal and testing plan agreed with the window supplier.
Frequently asked questions
How should the junction between an exposed-aggregate pool finish and an acrylic or glass window be detailed?
Detail it on the construction drawings before site work: a defined substrate rebate or termination edge, a flexible sealant recess confirmed by the window supplier and the project designer, named responsibilities for each trade, panel protection during works, and a wet physical sample and on-site mock-up of the termination. The shell waterproofing and the window's engineered sealing are separate scopes, completed, water-tested and accepted before the decorative finish is applied.
Does an exposed-aggregate finish waterproof the junction around an underwater window?
No. A cement-based exposed-aggregate finish such as PebbleCrete is a decorative layer, not a waterproofing barrier. The perimeter sealant’s watertightness role must be defined by the window supplier and project designer, while shell waterproofing and engineered window sealing arrangements are separate scopes that must be completed, water-tested at the stage agreed by the pool designer before work is covered, and accepted before finishing.
Why is a flexible sealant joint required between the pool finish and the acrylic or glass panel?
Concrete shells, cementitious finishes and acrylic or glass panels move differently under water load and temperature changes. A defined rebate with a flexible sealant joint confirmed by the project designer and window supplier helps accommodate specified differential movement, limiting stress transfer to the panel and reducing the risk of the finish edge spalling.
How should the project team judge the completed window junction at handover?
Assess the junction against the coordinated drawings, approved wet PebbleCrete sample and mock-up. Verify a straight termination edge, appearance within agreed natural and hand-applied variation, a continuous and evenly finished sealant profile with no visible voids or detachment (plus any required verification records), and an unmarked panel once protection is removed.
Photographs and screen colours are illustrations. Confirm colour and texture with a current physical sample viewed wet and an approved on-site mock-up.
More in the Knowledge Centre · Ask a technical question
This article provides general technical guidance, not a design, installation or safety instruction for a specific pool. Every project depends on its structure, substrate, waterproofing, water conditions and local regulations. Refer to the current PebbleCrete technical documents: the Technical Data Sheet and the Installation Overview are available online, and the Safety Data Sheet and the full Method Statement are issued on request. Confirm structural, waterproofing, electrical and installation decisions with qualified professionals. PebbleCrete supplies the material only; unless agreed otherwise in writing, substrate preparation and application are carried out by the owner’s applicator, who is responsible for that work. Nothing in this article limits your statutory rights.